Replacement of the "Burgsteges" in Alzenau
Trough Bridge over the Creek Kahl
Description
For the 35-year-old “Burgsteg” in Alzenau a replacement construction was necessary. This takes up the old design of the “Burgsteg” footbridge. Due to the media guidance within the bridge, it was not possible to lift prefabricated bridge sections, so that as far as possible prefabricated individual parts had to be mounted on site and around the existing pipelines. For this purpose, the sheet steel fittings as well as the handrail of the predecessor bridge were edited and pre-assembled in the factory to the new bridge components.
Client
City Alzenau
Year of Construction
2017
Planning
ALS Ingenieure GmbH & Co.KG
Constructor
Schaffitzel Holzindustrie GmbH & Co. KG
Dimensions
Length: 50,35 m
Width: 2,10 m
Construction
Trough bridge with externally braced, block-laminated main girders made of spruce Glulam and laterally cantilevered cross members. Use of edited steel parts of the previous bridge.
Our service
factory planning